The Florida Division of Administrative Hearings (DOAH) recently issued a bid protest decision on an important procedural issue. In Cross Constr. Servs., Inc. v. Dep’t of Transp., No. 20-4214BID, 2020 WL 7425244 (Fla. Div. Admin. Hrgs. Dec. 14, 2020) (RO), ALJ Bogan found it was not arbitrary, capricious, or otherwise improper for an agency to reject all offers in response to an untimely bid protest. In practical terms, this means that even if a protester’s allegations are untimely, it may still be worth it to file a protest if the issue is significant (although in such instances protesters should know they cannot “win” the protest, the agency must “voluntarily” correct the error).
In Cross Constr., a bidder whose bid was rejected as unbalanced filed a bid protest that was one day late. The agency nonetheless reviewed the allegations, and determined the RFP contained material ambiguities that may have prevented a fair competition. As a result, the agency decided to reject all offers and resolicit. The original awardee protested the decision to reject all, arguing the agency had acted arbitrarily and unlawfully by “us [ing an untimely] protest as the impetus to more closely scrutinize the bidders’ proposals and the language of the RFP.”
ALJ Bogan rejected this argument as a matter of law, holding “The fact that a bidder may have waived its right to protest by filing an untimely petition does not itself preclude Department action to reject all bids on the ground that the RFP was flawed.” (alterations omitted).
It is well-established that agencies have broad discretion to correct procurement errors. E.g. GTECH Corp. v. State, Dep’t of Lottery, 737 So. 2d 615 (Fla. 1st DCA 1999). It is equally well-established agency procurement actions may not be overturned if they are reasonable, and do not violate a specific statute or regulation. Dep’t of Transp. v. Groves-Watkins Constr., 530 So. 2d 912, 913 (Fla. 1988).
Whether a protest is timely and whether a protest has merit are separate issues. Moreover, on its face a decision to correct a significant potential procurement error that may have prevented an agency from obtaining best value is reasonable. Finally, while section 120.57(3), Fla. Stat. states untimely protests are waived by the protester, there is nothing in the statute that says an agency may not correct errors just because they are brought to its attention in an untimely protest. Hence it is entirely proper to take voluntary corrective action in response to a meritorious, albeit untimely, protest. Volume Servs. Div. of Interstate United Corp. v. Canteen Corp., 369 So. 2d 391, 395 (Fla. 2d DCA 1979) (in “the absence of specific constitutional or statutory requirements, a public agency” “may contract in any manner not arbitrary or capricious.”).
ALJ Bogan’s decision is also consistent with federal bid protest caselaw. The GAO has consistently held “it is within an agency’s discretion to take corrective action regardless of whether a protest was timely; all that is required is that the agency have reasonable concerns that errors in the procurement occurred.” Jones Lang LaSalle Americas, Inc., B-406019.2, 2012 WL 696502, at *4 (Comp. Gen. Feb. 14, 2012). Cf. Optimum Mgt. Sys., LLC, B-299322.3, 2007 WL 1703677, at *2 (Comp. Gen. May 23, 2007) (“OMS first asserts that the agency should not have taken corrective action because SofTec’s protest was untimely filed. We disagree. It was within the agency's discretion to take corrective action in connection with the procurement regardless of whether SofTec's protest was timely; all that is required is that the agency have reasonable concerns that errors in the procurement occurred.”).
To be sure, there may be some cases in which a decision to reject all bids is substantively improper. But, the timeliness of a bid protest that was the catalyst (or “impetus”) for such a decision should not be a material factor in such an inquiry.
Affected contractors or government agencies may contact Joseph M. Goldstein or Diana C. Mendez for assistance. The attorneys at Shutts & Bowen have substantial experience in proactively and practically handling the challenges and issues faced by contractors providing and agencies procuring the entire spectrum of goods and services (including construction) in a timely and cost-effective manner.
- Partner
Joseph M. Goldstein is the Managing Partner of the Fort Lauderdale office of Shutts & Bowen LLP, where he is a member of the Business Litigation Practice Group. Joseph also practices out of the Tallahassee office.
A ...
Search Blog
Follow Us
Recent Posts
- What You Need to Know About the U.S. Department of Transportation’s Build America TIFIA Loan
- Breaking News: Federal Judge Blocks Nationwide Implementation of the FTC’s New Rule Banning Noncompete Agreements
- September 4th is Almost Here: How Employers Can Prepare for the Upcoming Effective Date of the FTC’s Non-Compete Rule
- Florida’s New Statutory Home Warranty: What Home Builders Need to Know
- Orange County Proposes Temporary Suspension Ordinance on New Development Applications
- Raising the Roof: The U.S. Department of Labor Announces Rule Raising Salary Thresholds for Overtime Exemptions
- New Guidelines Anticipated Following HHS’s Health Cybersecurity Concept Paper
- SECURE 2.0 and Protecting Your Designated Beneficiaries
- Florida Appellate Court Provides Further Guidance Regarding New Summary Judgment Rule
- Pith? Perfect for Lienors, Not So Much for Landlords: Protecting Rights When Improvements Are Made to Commercial Tenancies
Popular Categories
- Employment and Labor
- Construction
- Business of Real Estate
- Litigation (Labor & Employment)
- Construction Litigation
- Competition
- Landlord-Tenant
- Real Estate Law
- Public Private Partnership
- Cybersecurity
- Intellectual Property
- Construction
- Appeals
- Development/Land Use
- Litigation
- Public Finance
- Contracts
- Trusts and Estates
- Data Security
- Business
- Supreme Court
- Privacy
- Technology
- Litigation (Appellate)
- IP Litigation
- Patents
- Business
- Regulatory Compliance
- Florida Government Contracts
- Health Care
- Foreclosures
- Trademark
- Contracting
- Financial Institutions
- Compliance
- Estate planning
- International Dispute Resolution
- Property Tax
- Conveyances
- Florida Public Contracts
- Government Contracting
- Government Contracts
- Government
- Lease
- Appellate Blog
- Patent Office
- Insurance
- Wealth planning
- Federal Government Contracting
- Cyber fraud
- Florida Bid Protests
- Public Contracts
- Infringement
- Proposal Writing
- Public Bidding
- GAO
- International Arbitration and Litigation
- Arbitration
- Bid Protest
- International
- Americans with Disabilities Act
- Restrictive Covenants
- Grant Writing
- Copyright
- Title
- Promissory Notes
- Small Business
- Florida Procurement
- Public procurement
- Consumer Privacy
- PTAB
- General Liability
- Technology
- International Arbitration
- Liens
- Liens and encumbrances
- Creditor's Rights
- Bidding
- Attorneys' Fees
- Inter Partes Review
- Power Generation
- Consumer Protection
- Regulation
- Contracting
- Government Vendor
- State Government Contracts
- Venue
- Ad Valorem Assessments
- Florida Administrative Law
- Attorneys' Fees
- Florida Rules of Appellate Procedure
- Bankruptcy
- Florida Public Procurement
- Russia-Related Arbitration
- Mortgages
- Eviction
- FINRA
- Record on Appeal
- Rehearing
- Loan guaranties
- Patents - Assignor Estoppel
- Dispute Resolution
- Statute of limitations
- Statute of repose
- Maritime
- Liens
- Damages
- Briefing
- Patents - Obviousness
- Request for Proposal
- Department of Labor
- Trade Secrets
- Commercial Brokerage
- Bid Writing
- Florida Bidding Strategies
- Renewal
- Attorneys' Fees
- Florida County Lands
- Florida Economic Incentive Packages
- Jury Instructions
- Stay
- Design Professionals
- Certiorari
- email hacking
- Forum Selection
- Offers of Judgment
- Prevailing Party
- Settlements
- Assignment of Contract
- Assignment of Proceeds
- Lis Pendens
- Banking
- Designer Liability
- Finality
- Fintech
- Appellate Jurisdiction - Deadlines
- Evidence
- Evidence
- Expert
- Expert Science
- Federal Rules of Appellate Procedure
- Federal Supply Schedule
- Florida Public Records Law
- Marketing/Advertising
- Mootness
- Preservation
- Socio-Economic Programs
- Sunshine Law
- Unlicensed Contracting
- Veteran Owned Business
- Partnerships and LLCs
- Homestead
- Standing
Editors
- Of Counsel
- Partner
- Partner
- Partner
- Partner
- Partner
- Partner
- Partner
- Partner
- Associate
- Partner
- Partner
- Partner
- Partner
- Senior Associate
- Partner
- Associate
- Partner
- Senior Associate
- Partner
- Associate
- Partner
- Partner
- Partner
- Partner
- Partner
- Partner
- Partner
- Partner
- Partner
- Partner
- Partner
- Partner
- Partner
- Partner
- Partner
- Partner
- Of Counsel
- Senior Associate
- Partner
- Associate
- Partner
- Partner
- Associate
- Partner
- Partner
- Partner
Archives
- September 2024
- August 2024
- June 2024
- May 2024
- February 2024
- November 2023
- August 2023
- July 2023
- June 2023
- May 2023
- April 2023
- February 2023
- January 2023
- December 2022
- November 2022
- October 2022
- September 2022
- August 2022
- July 2022
- June 2022
- May 2022
- April 2022
- March 2022
- February 2022
- January 2022
- December 2021
- October 2021
- September 2021
- August 2021
- July 2021
- June 2021
- May 2021
- April 2021
- March 2021
- February 2021
- January 2021
- December 2020
- October 2020
- September 2020
- August 2020
- July 2020
- June 2020
- May 2020
- April 2020
- March 2020
- February 2020
- January 2020
- October 2019
- August 2019
- July 2019
- May 2019
- April 2019
- March 2019
- February 2019
- January 2019
- December 2018
- November 2018
- October 2018
- September 2018
- August 2018
- July 2018
- June 2018
- May 2018
- April 2018
- March 2018
- February 2018
- January 2018
- December 2017
- November 2017
- October 2017
- September 2017
- August 2017
- July 2017
- June 2017
- May 2017
- April 2017
- March 2017
- February 2017
- January 2017
- December 2016
- November 2016
- October 2016
- September 2016
- August 2016
- July 2016
- June 2016
- May 2016
- April 2016
- March 2016