The law of contract formation allows parties “freedom to contract” in most aspects of transactions, services and/or liabilities. In the area of construction law, general contractors have largely negotiated a shift in the distribution of risk away from the general contractor and to the subcontractor with the inclusion of “pay-if-paid” contractual clauses that make the general contractor’s receipt of payment from the owner a condition precedent to the general contractor’s ultimate payment to the subcontractors. Absent such a provision, general contractors bear the risk of an owner’s potential insolvency.
Due to the rise of such provisions in construction contracts in recent years, subcontractors have sought to circumvent contractual “pay-if-paid” provisions by bringing claims against both the general contractors and their sureties who may guarantee payment. While the “pay-if-paid” clause may be cited by the general contractor as an affirmative defense where there has been no payment made by the owner, the effectiveness of such a defense by the general contractor’s surety is still an open question. One issue is whether such a defense would be available to a surety not in privity-of-contract with the parties during the negotiation and formation of the subcontract. Courts are split on this question. In OBS Co. v. Pace Constr. Corp., 558 So. 2d 404, 408 (Fla. 1990), the Florida Supreme Court explained that “[t]he payment bond is a separate agreement, and any liability to proceed against the general contractor does not necessarily prevent recovery against the sureties under the bond”. In OBS, recovery under the payment bond was not conditioned on the owner making final payment to the subcontractor and the bond did not incorporate the subcontract’s payment terms. Id. The Florida Supreme Court went on to note that “it would be inequitable to nullify the bonding company’s liability because the owner has not paid the contractor” and “[w]hen a surety on a private construction project issues a bond that purports to protect against mechanic’s liens, the bond must be construed and applied in accordance with the conditions of section 713.23, Florida Statutes”. Id.
Contrarily, other courts have ruled that the surety stands in the shoes of the general contractor and thus is afforded all the contractual defenses of the general contractor. In Great Am. Ins. Co. v. Sch. Bd. of Broward County, 2010 U.S. Dist. LEXIS 120030, *45, 2010 WL 4366865 (S.D. Fla. July 30, 2010), the United States District Court for the Southern District of Florida stated that once a surety has fulfilled its obligations under the bond, “the surety confers a benefit upon the obligee . . . . That benefit relieves the obligee of the burden of completing the construction". Id.; see also International Fid. Ins. Co. v. Cty. of Rockland, 98 F. Supp. 2d 400, 429, 2000 U.S. Dist. LEXIS 7454, *87 (S.D.N.Y. 2000). In short, these courts have interpreted the principal’s rights as shifting to the surety.
While it is unclear whether, absent clear and unequivocal language supplementing the subcontract to include this additional condition precedent, credence will be given to the surety’s affirmative defense under the general contractor's “pay-if-paid” contractual terms, we can be certain of more litigation in the near future pertaining to the applicability and extension of “pay-if-paid” clauses. In the interim, due diligence during contract formation is crucial in avoiding certain pitfalls.
Search Blog
Subscribe Today
Follow Us
Recent Posts
- Pith? Perfect for Lienors, Not So Much for Landlords: Protecting Rights When Improvements Are Made to Commercial Tenancies
- Risks & Rewards of 3D Printing in the Construction Industry
- Back to (Construction) Work after COVID
- Drones in the Construction Industry
- COVID-19 Stimulus Relief and the Construction Industry
- PFAS Liability Litigation and the Construction Industry – Act Now or Pay Later
- How Evolving Technology Is Disrupting the Construction Sector
- Remaining Vigilant: Hurricane Planning in the Construction Industry
- COVID-Confusion: Force Majeure and Executive Orders
- Top Florida Legislation Affecting the Construction Industry in 2020
Popular Categories
- Construction Litigation
- Construction
- Construction
- Business of Real Estate
- Landlord-Tenant
- Liens
- Real Estate Law
- Contracting
- Business
- Contracts
- General Liability
- Compliance
- Technology
- Florida Public Contracts
- Litigation
- Venue
- Insurance
- Privacy
- Technology
- Statute of limitations
- Statute of repose
- Florida Procurement
- Florida Public Procurement
- Public procurement
- Liens
- Contracting
- Federal Government Contracting
- Florida Government Contracts
- Public Contracts
- Damages
- Regulatory Compliance
- Small Business
- Design Professionals
- Forum Selection
- Attorneys' Fees
- Offers of Judgment
- Prevailing Party
- Settlements
- Designer Liability
- Business
- Regulation
- Unlicensed Contracting
- Evidence
- Expert Science
Editors
- Partner
- Partner
- Partner
- Partner
- Partner
- Partner
- Partner
- Partner
- Of Counsel
- Partner
- Partner
- Partner
- Partner
Archives
- August 2023
- November 2022
- July 2021
- June 2021
- March 2021
- February 2021
- December 2020
- October 2020
- September 2020
- August 2020
- July 2020
- May 2020
- April 2020
- March 2020
- December 2018
- October 2018
- September 2018
- August 2018
- July 2018
- June 2018
- May 2018
- April 2018
- January 2018
- November 2017
- October 2017
- August 2017
- June 2017
- May 2017
- April 2017
- March 2017
- February 2017
- January 2017
- December 2016
- November 2016
- October 2016